Town of Avon

For Immediate Release
May 12, 2017

2017 Microsurface Project to Begin May 15th


Avon, CO—Starting Monday, May 15th and continuing through June 2nd, the Town of Avon will be constructing street improvements on West Beaver Creek Boulevard from Lake Street to the railroad tracks, Wildridge Road between Wildwood Road and Old Trail Road, and along Millie’s Lane. The improvements include crack repair, asphalt patching, microsurface application consisting of a sealer with fine aggregate, and striping.  Project duration is approximately three weeks and will be performed by A-1 Chipseal & Rocky Mountain Pavement on behalf of the Town. 
 
The following is a description of the work with approximate start dates:

  1. Asphalt patching and crack sealing: Week of May 15th

  2. Microsurface application: Week of May 22nd

  3. Striping: Week of May 29th (No work on Memorial Day Holiday)

The contractor and Town staff will coordinate with residents and businesses in the immediate work areas.  Residents and guests are asked to drive carefully around construction personnel and equipment, and exercise patience as there will be some traffic delays on the roads under construction.  Please contact Jim Horsley, Town of Avon Project Engineer, with any questions regarding this work at (970) 748-4134 or jhorsley@avon.org.

# # #

Powered by CivicSend - A product of CivicPlus